Public Way Impacts

  • Harvard/Cambridge Police details will be posted at each intersection of Bow Street, Linden Street and Plympton Street.
  • Bow Street will remain closed in front of Randolph Hall from Linden to Plympton Street.
  • Linden Street will periodically be blocked to vehicle traffic for dumpster swaps, deliveries, and to move machinery.
  • A site fence has been installed, including lighting and signage.
  • Dumpster swaps will continue at the north end of Plympton Street, Bow Street, and the courtyard.
  • Continuous deliveries will happen at Linden, Plympton, and Bow Streets.
  • Plympton Street will be closed to vehicle traffic Monday, November 14 from 7:00 AM – 3:00 PM for concrete placement in the basement. Vehicles will be detoured down Mt Auburn Street to access Mass. Ave. The sidewalk will remain open for pedestrians and Plympton Street will re-open at the end of the workday.

 Exterior Site Activities

  • Utility work will continue to take place in the courtyard.
  • Work on a sewer line within the site fence will occur on Plympton Street.
  • Masonry work will continue.
  • Installation of the snow fence rails at the roof is ongoing.
  • Work activities on the wall foundations and stairs will occur in the courtyard.

 Interior Site Activities

  • Framing will continue to take place on the ground floor and in the basement.
  • Insulation and framing on the 4th floor is ongoing.
  • Taping, plastering, and finishing will continue on the 1st and 2nd floors.
  • Installation of bathroom vanity tops and brackets on the 3rd floor is ongoing.
  • Wood flooring will be installed on the 2nd floor.
  • Stair restorations will continue.
  • Installation of trim on the 2nd and 3rd floor is ongoing.
  • Tile will continue to be installed on the 1st and 2nd floor.
  • Elevator installation is ongoing.
  • Installation of risers for electrical, plumbing, mechanical, and fire protection will continue, as well as overhead rough-ins.