Week of November 28, 2022

Public Way Impacts

  • Harvard/Cambridge Police details will be posted at each intersection of Bow Street, Linden Street and Plympton Street.
  • Bow Street will remain closed in front of Randolph Hall from Linden to Plympton Street.
  • Linden Street will periodically be blocked to vehicle traffic for dumpster swaps, deliveries, and to move machinery.
  • A site fence has been installed, including lighting and signage.
  • Dumpster swaps will continue at the north end of Plympton Street, Bow Street, and the courtyard.
  • Continuous deliveries will happen at Linden, Plympton, and Bow Streets.

 Exterior Site Activities

  • Utility work will continue to take place in the courtyard.
  • Work on a sewer line within the site fence is ongoing on Plympton Street.
  • Masonry work is ongoing.
  • Work activities on the wall foundations and stairs will continue to occur in the courtyard.
  • Installation of balconies on Linden Street continues.
  • Work on the courtyard foundation will occur.

 Interior Site Activities

  • Spray insulation is ongoing on the ground floor and in the basement.
  • Taping, plastering, and finishing will continue on the 1st and 2nd floors.
  • Tile will continue to be installed on the 1st and 2nd floor.
  • Wood flooring continues to be installed on the 2nd floor.
  • Installation of trim on the 2nd floor is ongoing.
  • Stairs will continue to be restored and installed.
  • Elevator installation is ongoing.
  • Installation of risers for electrical, plumbing, mechanical, and fire protection will continue, as well as overhead rough-ins.