Week of April 10, 2023

Crews continue work on the Western Avenue utility crossing which involved temporarily relocating a section of Kresge Way last summerPedestrian and vehicular shifts on Western Avenue to accommodate underground utility trenches and work zones are in place. The work will continue into spring 2023 and is being coordinated with University operations.

Kresge Way Temporary Relocation

As part of Harvard’s infrastructure improvements in Allston, the University is extending thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western Avenue to Kresge Way, the main driveway into the HBS campus. An interim drive further west off Western Avenue has replaced the original drive.

Western Avenue Utility Crossing

Work for the utility crossing at Western Avenue will allow for expansion of the Harvard’s Allston energy infrastructure and is expected to be complete in the spring. Supporting vehicular, cycling and pedestrian flow, a phased approach is being used to install hot water and chilled water supply and return piping, telecommunications and electrical duct banks across the width of Western Ave. The construction activity consists of six phases to excavate trenches the width of Western Avenue. Only a third of the roadway is a construction zone allowing for two, open vehicular traffic lanes at all times, one in each direction.

  • A detailed traffic management plan is in place always maintaining two lanes of traffic.
  • The work zone is currently on the northern side of Western Avenue. Crews are backfilling the western trench.
  • The work zone will switch to the middle of the road at the end of next week for backfilling.
  • Crews will restore the northern sidewalk.
  • Pedestrians have been rerouted to the sidewalk adjacent to Kresge Way and the Harvard Business School lot. The sidewalk closest to the ERC site remains open.
  • Abutters can anticipate intermittent noise during excavation including use of a vacuum truck.
  • Appropriate signage and police details or workers will be in place. Work is scheduled to take place in close coordination with Harvard Business School/Housing/Transportation operations.
  • Saturday work will take place on April 8.
  • During project hours Monday through Friday from 7AM to 3PM (at times may extend to 6PM), the work will generate noise due to the presence of work crews and the use of construction equipment.

DEF Thermal, Utility Installation and Road Work

  • The interim DEF access drive behind the construction fence at the Enterprise Research Campus (ERC) has shifted off Western Avenue to Trotting Avenue near Hague Street as crews work on Milestone Street (the former East Drive).
  • All are working in coordination with National Resilience.
  • Other utility work installation continues inside the ERC site including a large drainage pipe (NASDEP) and a gas main service.

South Campus Drive Utility Work

The section of South Campus Drive and the sidewalk near the McCurdy Track that was closed, is restored and reopened. Tele/com utility work activity will continue on the closed diversion roadway.

  • The work will generate intermittent noise due to the presence of work crews and the use of construction equipment including excavators, and a possible vacuum truck needed to perform this work.
  • Work hours will be Monday through Friday from 7AM to 3PM with intermittent coordinated Saturday work.

92 Seattle Street

  • Fencing has been installed around the perimeter as crews prepare for the upcoming renovation project.  

Western Avenue Steam Manhole Repair

Nighttime repair work on a steam manhole on Western Avenue closer to the Charles River continues to take place from 7PM to 7AM intermittently for the next month. The work zone will be coned off while work is underway and opened during the day.

175 North Harvard Street

  • A diseased tree in poor condition was removed.