Week of May 8, 2023

Crews continue work on the Western Avenue utility crossing which involved temporarily relocating a section of Kresge Way last summerPedestrian and vehicular shifts on Western Avenue to accommodate underground utility trenches and work zones are in place. The work will continue into spring 2023 and is being coordinated with University operations.

Kresge Way Temporary Relocation

As part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western Avenue to Kresge Way, the main driveway into the HBS campus. An interim drive further west off Western Avenue has replaced the original drive.

Western Avenue Utility Crossing

Work for the utility crossing at Western Avenue will allow for expansion of Harvard’s Allston energy infrastructure and is in the final phase of work. Supporting vehicular, cycling and pedestrian flow, a phased approach is being used to install hot water and chilled water supply and return piping, telecommunications and electrical duct banks across the width of Western Ave. The construction activity consists of six phases to excavate trenches the width of Western Avenue. Only a third of the roadway is a construction zone allowing for two, open vehicular traffic lanes at all times, one in each direction.

  • A detailed traffic management plan is in place always maintaining two lanes of traffic.
  • The work zone is currently on the southern (ERC site) side of the roadway for crews to complete backfilling the western trench next week.
  • The southern sidewalk has closed in coordination with the work zone. All pedestrians will be guided to use the sidewalk adjacent to Harvard Business School.
  • Sidewalks will continue being restored.
  • A Harvard University IT duct bank and manhole installation will take place on the sidewalk adjacent to the Soldiers Field parking garage off Kresge Way near Western Avenue. The line from the duct bank will connect to the garage. This work activity will result in a shift of the pedestrian path for most of next week and into the following week. Upon completion the work zone will be restored. A HUPD detail and appropriate signage will direct pedestrians around this work zone.
  • Preclearing will take place in the northeastern corner of the ERC site in preparation for duct bank installation near the National Resilience driveway.   
  • Appropriate signage and police details or workers will be in place. Work is scheduled to take place in close coordination with Harvard Business School/Housing/Transportation operations.
  • No work will take place this Saturday, May 6.
  • During project hours Monday through Friday from 7AM to 3PM (at times may extend to 6PM), the work will generate noise due to the presence of work crews and the use of construction equipment.

DEF Thermal, Utility Installation and Road Work

  • The interim DEF access drive behind the construction fence at the Enterprise Research Campus (ERC) has shifted off Western Avenue to Trotting Avenue near Hague Street as crews work on Milestone Street (the former East Drive).
  • All are working in coordination with National Resilience.
  • Other utility work installation continues inside the ERC site including a large drainage pipe (NASDEP).
  • Finish grading and paving of roadway sections will take place inside the site on Monday, May 8 and Tuesday, May 9. 

South Campus Drive Utility Work

The section of South Campus Drive and the sidewalk near the McCurdy Track that was closed, is restored and reopened. The interim roadway will remain in place for use in future demolition/construction/utility work.

92 Seattle Street

Fencing has been installed around the perimeter as crews prepare for the upcoming renovation project.  

Western Avenue Steam Manhole Repair

The intermittent nighttime repair work, from 7PM to 7AM, on a steam manhole on Western Avenue closer to the Charles River is finishing up. The work zone will be coned and barreled off while work is underway and opened during the day.

175 North Harvard Street

Project trailers remain occupied in the 201 Western Avenue lot.