Week of July 3, 2023

The Western Avenue utility crossing roadway work is finalized and is extending onto Kresge Way. This work will continue into fall 2023 and is being coordinated with University operations.
 
Kresge Way Temporary Relocation
As part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western Avenue to Kresge Way, the main driveway into the HBS campus. An interim drive further west off Western Avenue has replaced the original drive.
 
Western Avenue Utility Crossing
The utility crossing at Western Avenue is complete. Final roadway paving is being coordinated.

Kresge Way Gas Line Relocation Phase 2 and Extension of Thermal Pipes and Electrical Duct Bank
Construction work is underway on the Kresge Way Gas Line Relocation Phase 2 and Extension of Thermal Pipes/Electrical Duct Bank.

  • A section of Kresge Way will shift west away from the Soldier’s Field Garage.
  • The road will be striped and appropriate signage will be in place.
  • Minor pathway shifts will also occur.
  • Starting next week, an interim parking attendant’s booth on the shifted section of Kresge Way will be operational.
  • The existing overhead sign will be removed and protected during construction.
  • National Grid gas crews are working on site relocating piping.
  • Crews are pre-clearing and excavating for the thermal utility work.
  • Construction is being phased in smaller segments to minimize impacts to visitors, pedestrians, bicycles, and vehicles.
  • Appropriate signage and police details or workers will be in place. Work is scheduled to take place in close coordination with Harvard Business School/Housing/Transportation operations.
  • During project hours Monday through Friday from 7AM to 3PM (at times may extend to 6PM), the work will generate noise due to the presence of work crews and the use of construction equipment.

DEF, ERC and Road Work

  • National Grid is working on Western Avenue between Trotting Avenue and Kresge Way on the ERC side of the road for the next month excavating and installing piping for an upsized gas service.  
  • The interim DEF access drive behind the construction fence at the Enterprise Research Campus (ERC) currently on Trotting Avenue will relocate back to Milestone Street.
  • The ERC development team has mobilized and is pre-clearing.
  • All are working in coordination with National Resilience.

92 Seattle Street

  • Fencing has been installed around the perimeter as crews start work on this renovation project.  
  • A new street signage package has been installed to help prevent construction vehicles and all other vehicular traffic from cutting through the Allston neighborhood.
  • Drilling mini piles inside the building will take place.

175 North Harvard Street

  • Project trailers remain occupied in the 201 Western Avenue lot. 
  • Temporary electrical pad areas are being finalized.
  • Crews will mobilize July 5 for interior abatement of the building.
  • Fencing will be installed.

210 North Harvard Street
Work on this exterior and interior improvement project has begun. 

  • Exterior work includes excavation for utilities and work at the street sidewalk and in the building’s parking lot.