Week of November 20, 2023

The following summarizes the work planned on the Adams House Phase 3 renovation for the week of November 20. Please note that items in BOLD are expected to generate some noticeable noise. 

PUBLIC WAY IMPACTS:

  • Continuous deliveries and dumpster swaps throughout the week.
  • Crew will be live loading demo debris from the back parking lot to a dumpster staged on Bow Street.
  • Stormwater system tie-in work will begin on Monday, November 20th, at the intersection of Bow Street and Arrow Street.
    • This work will continue throughout the week. 

EXTERIOR SITE ACTIVITIES:

  • Masonry work on the exterior façade will continue.
    • Washing activities will take place on the south and west elevations of Westmorly Hall.
  • Scaffolding installation will continue along North & West elevations of the Library.
  • Man/material hoist will be operating while the site is open.
    • On weekdays the lift will operate 7am-5pm and Saturday it will operate from 9am-4:30pm.
  • Dewatering equipment set up will continue at Russell Hall.
  • There will be a boom truck in the back parking lot placing steel throughout the week.

INTERIOR ACTIVITIES:

  • Interior rough carpentry will continue.
  • Interior demolition of Westmorly and Russell Halls.
  • Steel erection within Westmorly Hall will continue.
  • Saw cutting and removal of Russell Hall slab will continue.

WORK HOURS:

  • Monday to Friday: 7am to 3:30pm
  • Saturday 11/25 – 9am to 4:30pm