Week of December 4, 2023

The following summarizes the work planned on the Adams House Phase 3 renovation for the week of December 4th. Please note that items in BOLD are expected to generate some noticeable noise.
 
PUBLIC WAY IMPACTS:

  • Continuous deliveries and dumpster swaps throughout the week.
  • Crews will be live loading demo debris from the back parking lot to a dumpster staged on Bow Street.
  • Trucking of soils and concrete will continue from Gate 2 on Bow Street.
  • Eversource will continue working on the gas line at the Bow and Arrow Intersection.

EXTERIOR SITE ACTIVITIES:

  • Masonry work on the exterior façade will continue.
    • Masonry cutting work along the west and south elevations.
  • Scaffolding installation will continue on the west elevation.
  • Installation of manhole structures will continue at the East Terrace.
  • Excavation for foundations will continue in the Light Court/Conservatory Area.
  • Man/material hoist will be operating while the site is open.
    • On weekdays the lift will operate 7:00am-5:00pm and Saturday it will operation from 9:00am-4:30pm.
  • Dewatering set up will continue at Russell Hall.
  • Temporary roof install will continue for Westmorly Hall.
  • A crane will be staged within the fence line off Bow Street to remove debris from the Wesmorly Hall roof.
  • A crane is planned to place steel on the second floor out of the back parking lot at the end of the week.

INTERIOR ACTIVITIES:

  • Interior rough carpentry will continue.
  • Interior demolition of Westmorly and Russell Halls.
  • Steel erection within Westmorly Hall will continue.
  • Saw cutting and removal of Russell Hall slab and Westmorly Slab will continue.

WORK HOURS:

  • Monday to Friday: 7:00am to 3:30pm
  • Saturday 12/9-  9am to 4:30pm