Allston Development Monthly Update- December 2023

Bulk excavation operations have been completed on site. Two tower cranes have been erected and are operational. They are designed to move or “weathervane” in the wind. Concrete placement and rebar operations will be ongoing through the month. Crews are targeting December 14th to place concrete for the hotel core mat. This work is weather…Continue Reading Allston Development Monthly Update- December 2023

Week of December 4, 2023

The Western Avenue utility crossing roadway work is finalized and is extending onto Kresge Way. This work will continue into December 2023 and is being coordinated with University operations. Snow and ice plans are in place for the winter. Kresge Way Temporary RelocationAs part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from…Continue Reading Week of December 4, 2023