The Western Avenue utility crossing roadway work is finalized and is extending onto Kresge Way. This work will finish this winter and is being coordinated with University operations. Kresge Way Temporary RelocationAs part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western Avenue to Kresge Way, the…Continue Reading Week of February 26, 2024
Week of February 26, 2024
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of February 26th. Please note that items in BOLD are expected to generate some noticeable noise. PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of February 26, 2024
Week of February 19, 2024
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of February 19th. Please note that items in BOLD are expected to generate some noticeable noise. PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of February 19, 2024
Week of February 19, 2024
The Western Avenue utility crossing roadway work is finalized and is extending onto Kresge Way. This work will finish this winter and is being coordinated with University operations. Kresge Way Temporary RelocationAs part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western Avenue to Kresge Way, the…Continue Reading Week of February 19, 2024
Week of February 12, 2024
175 North Harvard Street Project Construction Impacts Update…Continue Reading Week of February 12, 2024
Week of February 5, 2024
175 North Harvard Street Project Construction Impacts Update…Continue Reading Week of February 5, 2024
Week of January 29, 2024
175 North Harvard Street Project Construction Impacts Update…Continue Reading Week of January 29, 2024
Week of February 12, 2024
The Western Avenue utility crossing roadway work is finalized and is extending onto Kresge Way. This work will finish this winter and is being coordinated with University operations. Kresge Way Temporary Relocation As part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western Avenue…Continue Reading Week of February 12, 2024
Week of February 12, 2024
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of February 12th. Please note that items in BOLD are expected to generate some noticeable noise. PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of February 12, 2024
Week of February 5, 2024
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of February 5th. Please note that items in BOLD are expected to generate some noticeable noise. PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of February 5, 2024