Week of March 11, 2024


The following summarizes the work planned on the Adams House Phase 3 renovation for the week of March 11. Please note that items in BOLD are expected to generate some noticeable noise.


PUBLIC WAY IMPACTS:
• Continuous deliveries and dumpster swaps will occur throughout the week.
• Trucking of soils and concrete will continue next week from Bow Street Gate 2.
• A concrete Pump Truck is scheduled for next week in the Rear Parking Lot.


EXTERIOR SITE ACTIVITIES:
• Masonry work on the exterior façade will continue with cutting along the East and South of Westmorly.
• The roofing contractor will continue abatement / demo of slate roof on the library.
• Scaffolding for Russell Hall chimney re-builds will finish up.

• Masonry demo for the Russell Hall chimneys will begin towards the end of the week.
• Crane activity for the chimney demo at Russell Hall and roof abatement at the library may be required towards the end of next week. The team will be notified once scheduled.
• Man/material hoist will be operating while the site is open.
On weekdays the lift will operate 7 a.m.- 3:30 p.m. and on Saturdays it will be in operation from 9 a.m. – 4:30 p.m.

INTERIOR ACTIVITIES:
• Interior wood framing will continue in Westmorly.
• Drywall and framing is ongoing within Westmorly.
• Excavations within Russell Halls’ basement will occur.
• Excavations for under slab utilities within Westmorly is progressing.
• Excavations for the new Elevator Pit will continue in Westmorly North.
• Excavations for new Elevator #1 in Westmorly South will take place.
• Rebar & concrete work is continuing.

• Mechanical contractors will continue with installation of new systems within Westmorly
• Scaffolding at the Pool Theater remains ongoing.

WORK HOURS:
• Monday to Friday: 7 a.m. to 3:30 p.m.
• Saturday 3/9: 9 a.m. to 4:30 p.m.