Week of March 18, 2024

PUBLIC WAY IMPACTS:

  • Continuous deliveries and dumpster swaps will occur throughout the week.
  • Trucking of soils and concrete will continue next week from Bow Street Gate 2.
  • A concrete Pump Truck is scheduled for next Wednesday (Gate 2 Bow Street).

EXTERIOR SITE ACTIVITIES:

  • Masonry work on the exterior façade will continue with cutting along the West & South elevation of the Library Commons, and the North & East elevation of Westmorly.
  • The roofing contractor will continue abatement / demo of slate roof on the library.
  • Masonry demo for the Russell Hall chimney’s will begin on Monday.
  • Crane activity for the chimney demo at Russell Hall and roof abatement at the library may be required towards the end of next week. The team will be notified once scheduled.
  • Man/material hoist will be operating while the site is open.
    1. On weekdays the lift will operate 7 a.m.-3:30 p.m. and on Saturday it will be in operation from 9 a.m.-4:30 p.m.

INTERIOR ACTIVITIES:

  • Interior wood framing will continue in Westmorly.
  • Drywall and framing remain ongoing within Westmorly.
  • Excavations within Russell Halls’ basement will occur.
  • Excavations for under slab utilities within Westmorly will continue.
  • Excavations for new elevator #1 in Westmorly South will take place.
  • Rebar and concrete work is continuing.
  • Mechanical Contractors will continue with the installation of new systems within Westmorly.
  • Scaffolding at the Pool Theater & Courtyard will continue.

WORK HOURS:

  • Monday to Friday: 7 a.m. to 3:30 p.m.
  • Saturday 3/23:  9 a.m. to 4:30 p.m.