Week of March 25, 2024

The following summarizes the work planned on the Adams House Phase 3 renovation for the week of March 25. Please note that items in BOLD are expected to generate some noticeable noise.

PUBLIC WAY IMPACTS:

  • Continuous deliveries and dumpster swaps will occur throughout the week.
  • Trucking of soils and concrete will continue next week from Bow Street Gate 2.
  • A concrete Pump Truck is scheduled for Tuesday, March 26 at Bow Street Gate 2.
  • Tuesday, March 26 a crane is scheduled to be on site in the rear parking lot.
  • Eversource will be working in the Bow Street and Arrow Street intersection starting on Monday, March 25. Work is expected to occur through Friday, March 29 with working hours 7 a.m. – 4 p.m.

 EXTERIOR SITE ACTIVITIES:

  • Masonry work on the exterior façade will continue with cutting along the West & South elevation of the library commons, and the North & East elevation of Westmorly.
  • The roofing contractor will continue abatement / demo of slate roof on the library.
  • Masonry demo for the Russell Hall chimneys continues.
  • Crane activity for the chimney demo at Russell Hall is ongoing.
  • Man/material hoist will be operating while the site is open.
    • On weekdays the lift will operate 7 a.m.-3:30 p.m. and on Saturdays it will be in operation from 9 a.m. -4:30 p.m.

INTERIOR ACTIVITIES:

  • Interior wood framing will continue in Westmorly.
  • Drywall and framing work is ongoing within Westmorly.
  • Excavations within Russell Halls’ basement will occur.
  • Excavations for under slab utilities within Westmorly is progressing.
  • Excavations for new Elevator #1 in Westmorly South will continue to take place.
  • Rebar & concrete work is continuing.
  • Mechanical contractors will continue with installation of new systems within Westmorly.
  • Scaffolding at the Pool Theater and Courtyard remains ongoing.

WORK HOURS:

  • Monday to Friday: 7 a.m. to 3:30 p.m.
  • Saturday March 30: 9 a.m. to 4:30 p.m.