Week of April 1, 2024

The following summarizes the work planned on the Adams House Phase 3 renovation for the week of April 1. Please note that items in BOLD are expected to generate some noticeable noise.
 

PUBLIC WAY IMPACTS:

  • Continuous deliveries and dumpster swaps will occur throughout the week.
  • Trucking of soils and concrete will continue next week from Bow Street Gate 2.
  • Rebar delivery is scheduled for Wednesday April 3.
  • A crane is scheduled to be on site in the rear parking lot. Date to be determined as this work activity is weather dependent.

EXTERIOR SITE ACTIVITIES:

  • Masonry work on the exterior façade will continue with cutting along the West & South elevation of the library commons, and the North & East elevation of Westmorly.
  • The roofing contractor will continue abatement / demo of slate roof on the library.
  • Masonry demo for the Russell Hall chimneys continues.
  • Crane activity for the chimney demo at Russell Hall is ongoing.
  • Abatement will continue for the exterior windows of the East and South elevations of Westmorly.
  • Man/material hoist will be operating while the site is open.
    • On weekdays the lift will operate 7 a.m.-3:30 p.m. and on Saturdays it will be in operation from 9 a.m. -4:30 p.m.

INTERIOR ACTIVITIES:

  • Interior wood framing will continue in Westmorly.
  • Drywall and framing work is ongoing within Westmorly.
  • Excavations within Russell Halls’ basement will occur.
  • Excavations for under slab utilities within Westmorly is progressing.
  • Rebar & concrete work is continuing.
  • Mechanical contractors will continue with installation of new systems within Westmorly.
  • Scaffolding at the Pool Theater and Courtyard remains ongoing.

WORK HOURS:

  • Monday to Friday: 7 a.m. to 3:30 p.m.
  • Saturday April 6: 9 a.m. to 4:30 p.m.