Week of December 19, 2022

Crews continue work on the Western Avenue utility crossing which involved temporarily relocating a section of Kresge Way in JulyPedestrian and vehicular shifts on Western Avenue to accommodate underground utility trenches and work zones will be in place. The work will continue into spring 2023 and is being coordinated with University operations.
 
Kresge Way Temporary Relocation
As part of Harvard’s infrastructure improvements in Allston, the University is extending thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western Avenue to Kresge Way, the main driveway into the HBS campus. An interim drive further west off Western Avenue has replaced the original drive.

Western Avenue Utility Crossing
Work for the utility crossing at Western Avenue will allow for expansion of the Harvard’s Allston energy infrastructure and is expected to be complete in the spring. Supporting vehicular, cycling, and pedestrian flow, a phased approach is being used to install hot water and chilled water supply and return piping, telecommunications and electrical duct banks across the width of Western Ave. The construction activity consists of six phases to excavate three trenches the width of Western Avenue. Only a third of the roadway is a construction zone allowing for two, open vehicular traffic lanes at all times, one in each direction.

  • A detailed traffic management plan is in place always maintaining two lanes of traffic.
  • Pedestrians will be allowed access to both sidewalks for work tomorrow, December 15, and early next week. Then all will shift later next week to the Harvard Business School sidewalk while crews finish backfilling the eastern trench and begin excavation on the western trench from the south side of Western Avenue along the ERC site.
  • Backfilling will continue on the east trench which runs across Western Avenue. Crews will have a work zone in the middle of the road starting tomorrow and into the week of December 18, backfilling on the ERC side of the road. The work zone will switch to this area and excavation will begin on the west trench. 
  • Abutters can anticipate intermittent noise during excavation including use of a vacuum truck.
  • Appropriate signage and police details or workers will be in place to provide guidance to pedestrians and vehicles. Work is taking place in close coordination with Harvard Business School/Housing/Transportation operations.
  • Work activity will take place on Saturday, December 17.
  • During project hours Monday through Friday, 7AM to 3PM (at times may extend to 6PM), the work will generate noise due to the presence of work crews and the use of construction equipment.

DEF Thermal and Utility Installation

  • The interim DEF access drive behind the construction fence at the Enterprise Research Campus (ERC) has opened up.
  • All are working in coordination with National Resilience.
  • Other utility work including a large drainage pipe installation (NASDEP) continues inside the ERC site.   

South Campus Drive Utility Work
A South Campus Drive diversion temporary roadway has opened while crews install utilities (thermal and ductbank) near the McCurdy Track. Vehicular, cycling, and pedestrian traffic has shifted from the new work zone and will be maintained throughout the work activity into spring 2023.

  • Excavation work is underway for the thermal pipe installation in the work zone behind the construction fencing.
  • The work will generate intermittent noise due to the presence of work crews and the use of construction equipment including excavators, and a possible vacuum truck needed to perform this work.
  • Work hours will be Monday through Friday, 7AM to 3PM with intermittent coordinated Saturday work.