Crews continue work on the Western Avenue utility crossing which involved temporarily relocating a section of Kresge Way last summer. Pedestrian and vehicular shifts on Western Avenue to accommodate underground utility trenches and work zones are in place. The work will continue into spring 2023 and is being coordinated with University operations. Kresge Way Temporary RelocationAs part…Continue Reading Week of May 1, 2023