Week of November 6, 2023

The following summarizes the work planned on the Adams House Phase 3 renovation for the week of November 6. Please note that items in BOLD are expected to generate some noticeable noise. 

PUBLIC WAY IMPACTS:

  1. Continuous deliveries and dumpster swaps throughout the week.
  2. Crew will be live loading demo debris from the back parking lot to a dumpster staged on Bow Street.
  3. Eversource is scheduled to remove the existing gas main at the intersection of Bow Street and Arrow Street on Monday 11/6 and Tuesday 11/7.  
    1. This is an Eversource project and is permitted separately from the Adams Phase 3 Project. 
    2. Following this work crews will complete a storm drain tie-in in this area.
    3. Jersey barriers along upper Bow Street will be reinstalled following this work.

 
EXTERIOR SITE ACTIVITIES:

  1. Masonry work on the exterior façade will continue.
  2. Scaffolding installation will continue along the west, south and east elevations of Westmorly Hall.
  3. Man/material hoist will be operating while the site is open.
    1. On weekdays the lift will operate 7:00am-5:00pm and Saturday it will operation from 9:00am-4:30pm.
  4. Steel erection at the fourth floor of Westmorly Hall will continue.
  5. Dewatering equipment will be delivered to the site to begin the dewatering process.
  6. Crews will make the final connections for temporary heating equipment and a gas meter in the alley between Adams House and 22 Plympton Street.

 
INTERIOR ACTIVITIES:

  1. Interior rough carpentry will continue.
  2. Interior demolition of Westmorly and Russell Halls.
  3. Steel erection within Westmorly Hall will continue.
  4. Saw cutting and removal of Russell Hall slab will continue.

 
WORK HOURS:

  1. Monday to Friday: 7:00am to 3:30pm

Saturday 11/11 – Site will be closed due to Veterans Day