Public Way Impacts Exterior Site Activities Interior Site Activities…Continue Reading Week of March 13, 2023
Week of March 13, 2023
Crews continue work on the Western Avenue utility crossing which involved temporarily relocating a section of Kresge Way last summer. Pedestrian and vehicular shifts on Western Avenue to accommodate underground utility trenches and work zones are in place. The work will continue into spring 2023 and is being coordinated with University operations. Snow removal will occur…Continue Reading Week of March 13, 2023
Week of March 6, 2023
Crews continue work on the Western Avenue utility crossing which involved temporarily relocating a section of Kresge Way last summer. Pedestrian and vehicular shifts on Western Avenue to accommodate underground utility trenches and work zones are in place. The work will continue into spring 2023 and is being coordinated with University operations. Snow removal will occur as…Continue Reading Week of March 6, 2023
Week of March 6, 2023
Public Way Impacts Exterior Site Activities Interior Site Activities…Continue Reading Week of March 6, 2023
Allston Development Monthly Update-March 2023
Enterprise Research Campus (ERC)* Phase 1 Enabling Infrastructure WorkEnabling work continues at the parcel of the future Enterprise Research Campus (ERC) in Allston across from Harvard Business School (HBS) bordered by the Mass Pike, Western Avenue, Hague Street, and the National Resilience Inc. facility at 500 Soldiers Field Road. Much of the project work, which…Continue Reading Allston Development Monthly Update-March 2023
Week of February 27, 2023
Crews continue work on the Western Avenue utility crossing which involved temporarily relocating a section of Kresge Way last summer. Pedestrian and vehicular shifts on Western Avenue to accommodate underground utility trenches and work zones are in place. The work will continue into spring 2023 and is being coordinated with University operations. Snow removal will occur…Continue Reading Week of February 27, 2023
Week of February 27, 2023
Public Way Impacts Exterior Site Activities Interior Site Activities…Continue Reading Week of February 27, 2023
Week of February 20, 2023
Public Way Impacts Exterior Site Activities Interior Site Activities…Continue Reading Week of February 20, 2023
Week of February 20, 2023
Crews continue work on the Western Avenue utility crossing which involved temporarily relocating a section of Kresge Way last summer. Pedestrian and vehicular shifts on Western Avenue to accommodate underground utility trenches and work zones are in place. The work will continue into spring 2023 and is being coordinated with University operations. Kresge Way Temporary Relocation…Continue Reading Week of February 20, 2023
Week of February 13, 2023
Public Way Impacts Exterior Site Activities Interior Site Activities…Continue Reading Week of February 13, 2023