175 North Harvard Street Project Construction Impacts Update…Continue Reading Week of February 19, 2024
Week of March 11, 2024
The Western Avenue utility crossing roadway work is finalized and is finishing up on Kresge Way and is being coordinated with University operations. Kresge Way Temporary RelocationAs part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western Avenue to Kresge Way, the main driveway into the…Continue Reading Week of March 11, 2024
Week of March 11, 2024
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of March 11. Please note that items in BOLD are expected to generate some noticeable noise. PUBLIC WAY IMPACTS:• Continuous deliveries and dumpster swaps will occur throughout the week.• Trucking of soils and concrete will continue next week from…Continue Reading Week of March 11, 2024
Week of March 4, 2024
The Western Avenue utility crossing roadway work is finalized and is extending onto Kresge Way. This work will finish this winter and is being coordinated with University operations. Kresge Way Temporary RelocationAs part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western Avenue to Kresge Way, the…Continue Reading Week of March 4, 2024
Week of March 4, 2024
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of Marth 4th. Please note that items in BOLD are expected to generate some noticeable noise. PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of March 4, 2024