The Western Avenue utility crossing roadway work is finalized and is extending onto Kresge Way. This work will finish this winter and is being coordinated with University operations. Kresge Way Temporary RelocationAs part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western Avenue to Kresge Way, the…Continue Reading Week of February 19, 2024
Week of February 12, 2024
The Western Avenue utility crossing roadway work is finalized and is extending onto Kresge Way. This work will finish this winter and is being coordinated with University operations. Kresge Way Temporary Relocation As part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western Avenue…Continue Reading Week of February 12, 2024
Week of February 5, 2024
The Western Avenue utility crossing roadway work is finalized and is extending onto Kresge Way. This work will finish this winter and is being coordinated with University operations. Kresge Way Temporary RelocationAs part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western Avenue to Kresge Way, the…Continue Reading Week of February 5, 2024
Week of January 29, 2024
The Western Avenue utility crossing roadway work is finalized and is extending onto Kresge Way. This work will finish this winter and is being coordinated with University operations. Kresge Way Temporary RelocationAs part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western Avenue to Kresge Way, the…Continue Reading Week of January 29, 2024
Week of January 22, 2024
The Western Avenue utility crossing roadway work is finalized and is extending onto Kresge Way. This work will finish this winter and is being coordinated with University operations. Kresge Way Temporary RelocationAs part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western Avenue to Kresge Way, the…Continue Reading Week of January 22, 2024
Week of January 15, 2024
The Western Avenue utility crossing roadway work is finalized and is extending onto Kresge Way. This work will continue this month and is being coordinated with University operations. Kresge Way Temporary RelocationAs part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western Avenue to Kresge Way, the…Continue Reading Week of January 15, 2024
Week of January 8, 2024
After hours snow removal work will take place through the winter months as inclement weather events occur. The Western Avenue utility crossing roadway work is finalized and is extending onto Kresge Way. This work will continue this month and is being coordinated with University operations. Kresge Way Temporary Relocation As part of Harvard’s infrastructure improvements in Allston, the…Continue Reading Week of January 8, 2024
Week of December 25, 2023 & January 1, 2024
The Western Avenue utility crossing roadway work is finalized and is extending onto Kresge Way. This work will continue into early 2024 and is being coordinated with University operations. Snow and ice removal plans are in place for all Allston projects. Kresge Way Temporary Relocation As part of Harvard’s infrastructure improvements in Allston, the University has extended thermal…Continue Reading Week of December 25, 2023 & January 1, 2024
Week of December 18, 2023
The Western Avenue utility crossing roadway work is finalized and is extending onto Kresge Way. This work will continue into fall 2023 and is being coordinated with University operations. Kresge Way Temporary RelocationAs part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western Avenue to Kresge Way,…Continue Reading Week of December 18, 2023
Week of December 11, 2023
The Western Avenue utility crossing roadway work is finalized and is extending onto Kresge Way. This work will continue into fall 2023 and is being coordinated with University operations. Kresge Way Temporary RelocationAs part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western Avenue to Kresge Way,…Continue Reading Week of December 11, 2023