175 North Harvard Street Project Construction Impacts Update • The job site will be closed on New Year’s Day, Monday, January 1. • Project enabling activities continue through January in preparation for building construction. o Building demolition activities are substantially complete. o The installation of sheet piles using a vibratory hammer will be ongoing for…Continue Reading Week of January 1, 2024
Week of January 1, 2024
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of January 1st. Please note that items in BOLD are expected to generate some noticeable noise. PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of January 1, 2024
Week of December 25, 2023
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of December 25th. Please note that items in BOLD are expected to generate some noticeable noise. PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of December 25, 2023
Week of December 25, 2023 & January 1, 2024
The Western Avenue utility crossing roadway work is finalized and is extending onto Kresge Way. This work will continue into early 2024 and is being coordinated with University operations. Snow and ice removal plans are in place for all Allston projects. Kresge Way Temporary Relocation As part of Harvard’s infrastructure improvements in Allston, the University has extended thermal…Continue Reading Week of December 25, 2023 & January 1, 2024
Week of December 25, 2023
175 North Harvard Street Project Construction Impacts Update •The job site will be closed on Monday, December 25, for the Christmas holiday. • Project enabling activities continue through January in preparation for building construction. o Sitework, including pre-excavation, concrete, and soil removal, will continue into next week. Truck activity will remain steady and street sweeping…Continue Reading Week of December 25, 2023
Week of December 18, 2023
175 North Harvard Street Project Construction Impacts Update • Sitework, including concrete and soil removal, will continue into early next week. Truck activity will remain steady and street sweeping will continue to support this work. •Project enabling activities continue through January in preparation for building construction. o Crews are grading the site down to the…Continue Reading Week of December 18, 2023
Week of December 18, 2023
The Western Avenue utility crossing roadway work is finalized and is extending onto Kresge Way. This work will continue into fall 2023 and is being coordinated with University operations. Kresge Way Temporary RelocationAs part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western Avenue to Kresge Way,…Continue Reading Week of December 18, 2023
Week of December 11, 2023
The Western Avenue utility crossing roadway work is finalized and is extending onto Kresge Way. This work will continue into fall 2023 and is being coordinated with University operations. Kresge Way Temporary RelocationAs part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western Avenue to Kresge Way,…Continue Reading Week of December 11, 2023
Week of December 18, 2023
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of December 18th. Please note that items in BOLD are expected to generate some noticeable noise. PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of December 18, 2023
Week of December 11, 2023
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of December 11th. Please note that items in BOLD are expected to generate some noticeable noise. PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of December 11, 2023